Completion reported · February 2, 2026
Provalus facility buildout
The June 2025 research describes the next phases of the facility at 1505 South Fourth Street. A later city record reports that the Provalus project was completed on time.
The February 2, 2026 minutes, included in the February 17 council packet, provide that update. They do not establish today’s hiring availability.
February 2, 2026 council minutes (February 17 packet, PDF page 4) · June 2025 background
Current status unconfirmed
A&A Texas Capital
The June 2025 research describes a lumber-treatment complex along Loop 304 and changes to its incentive agreement. The original newspaper report supports that historical account.
Current construction progress and an opening date are unconfirmed.
The Messenger, June 24, 2025
Registered plan · completion unconfirmed
United Ag & Turf renovation
TDLR’s January 15, 2025 registration describes a renovation at 1220 E. Loop 304. The filing estimates $1.8 million and lists an April 7, 2025–April 30, 2026 construction schedule.
The record says “Review Complete.” That is not proof that construction finished. Completion and current operating details remain unconfirmed.
TDLR TABS2025009607 · registered January 15, 2025
Registered plan · opening unconfirmed
Proposed AutoZone store
TDLR’s June 23, 2026 registration describes a new 7,009-square-foot AutoZone at 1150 E. Loop 304. The filing schedules construction from November 7, 2026, to March 12, 2027.
“Project Registered” does not establish that work has started. March 12 is a scheduled construction finish, not a confirmed store-opening date.
TDLR TABS2026023603 · registered June 23, 2026
Grant award unconfirmed
East Goliad sidewalks
The research describes a proposal to improve sidewalks and accessibility between Second and Fourth Streets. The March 2024 report confirms the earlier application effort.
The supplied 2026 hearing pages could not be verified. A grant award and construction schedule remain unconfirmed.
The Messenger, March 18, 2024
Application authorized · award unconfirmed
Town Branch flood and erosion work
February 2, 2026 council minutes record authorization to apply for GLO disaster-recovery funding for Town Branch Creek rehabilitation.
This confirms permission to apply. A funding award, construction start and completion date remain unconfirmed.
City council packet, PDF page 6
Funding approved · construction status unconfirmed
Water and wastewater investment
On September 12, 2024, TWDB approved $11,663,500 for wastewater planning, design and construction, including treatment-plant equipment and a collection-system study.
A separate $4,250,000 approval covers a new well, related transmission and treatment facilities, and an asset-management plan. Both packages combine financing and principal forgiveness; they are not entirely grants.
Current construction milestones and completion dates remain unconfirmed. The next update to watch is design and construction progress.
TWDB wastewater approval · September 12, 2024 · TWDB drinking-water approval · September 12, 2024
Work scheduled · November 23–27, 2026
Loop 304 and highway routes
TxDOT Minute Order 117052, dated September 25, 2025, moves the through routes of US 287, SH 7, SH 19 and SH 21 onto Loop 304 and redesignates the downtown segments as business routes.
A TxDOT Lufkin District release, republished by NacNewsNow on November 20, schedules barricade inspections and detail work on the SL 304 overlay for November 23–27, 2026. This is planned work for that week, not a completion report.
Final acceptance, percent complete and a current Loop 304-only contract cost remain unconfirmed.
TxDOT route order · September 25, 2025 (PDF) · TxDOT weekly release via NacNewsNow · November 20, 2026
Unconfirmed · source mismatch
School connectivity
The draft’s Region 16 EDNET item cannot be attributed to Crockett ISD. The linked BoardBook organization is Borger ISD.
A Crockett ISD fiber proposal, vote outcome and implementation schedule remain unconfirmed. School bond information is coming soon.
BoardBook organization 904: Borger ISD · Crockett ISD’s BoardBook archive (older meetings)
Mission verified · project dates TBD
Housing Authority modernization
The Crockett Housing Authority describes modernization of public housing as part of its mission. That statement does not establish a funded construction project or completion date.
Specific modernization milestones and new housing development details are coming soon.
Crockett Housing Authority